Indian firms hold about 4,700 MW of Nepal hydropower, but only one project is being built

Seven large projects have gone to Indian companies since the 2024 export deal, and the Kathmandu Post finds only Arun-III under construction.

BCEBEI

Indian companies hold seven major hydropower projects in Nepal with a combined capacity of around 4,700 megawatts, according to a Kathmandu Post report on 5 November 2026. Only one of the seven is under construction. That project, the 900 MW Arun-III, is the furthest along, while the others are still at earlier stages. For students, the report is a clear lesson in the difference between a project that has been awarded and one that is producing power.

  • 4,700 MWcombined capacity of seven projects held by Indian firms
  • 77.5%share of Arun-III's power generation work completed
  • 10,000 MWexport target over ten years under the January 2024 agreement

Seven projects, one construction site

The Kathmandu Post counted seven large hydropower projects that have gone to Indian developers, adding up to about 4,700 MW of planned capacity. That is a large share of the generation Nepal hopes to export. Yet the paper found that only one of these projects is currently being built.

A hydropower project passes through several stages before it makes electricity. Developers study the site, prepare the detailed design, secure environmental approval, sign a power purchase or export arrangement, raise money and then start civil works. Each stage can take years, and a project can stop at any of them.

So a capacity figure on paper says little about when power will flow. Megawatts that are awarded are not megawatts that are installed. The useful measure is how much work has been completed on the ground, and how close each project is to its first unit turning.

Arun-III is the one that is moving

The 900 MW Arun-III project in eastern Nepal is the one under construction. The Post reports that 77.5 percent of the power generation component and 60 percent of the transmission line component have been completed. Its latest completion deadline is mid-March 2028, and its estimated cost is Rs 144 billion.

The two progress figures tell different stories. The dam, tunnel and powerhouse are well advanced, but the line that carries the power out is further behind. A plant that finishes before its transmission line cannot deliver its full output, so the slower part sets the real finish date.

This is a common problem in Nepal's power sector. Generation and transmission are often planned and built on separate schedules. Engineers who manage a project have to track both, because a delay on either one holds back the revenue the whole investment depends on.

Money is arranged for Upper Karnali

The 900 MW Upper Karnali project, held by India's GMR, has not started construction, but its financing is taking shape. The company's documents show a loan of INR 65 billion from the Indian Renewable Energy Development Agency and Rs 20 billion from a consortium of Nepali banks.

Financing is often the step where large projects stall. A developer must convince lenders that the plant will be built on time, that it can sell its power and that the cost estimate is realistic. Arranged loans are a sign of progress, but they are not the same as work on site.

Another project, Lower Arun, was awarded to India's SJVN on 29 January 2021, with an estimated cost of Rs 92.67 billion. The Post's report does not show it under construction. Taken together, the projects show how long the path from award to building can be.

Why a finished plant may still wait

Building a plant is not the only condition for exporting its power to India. The Post notes that India has not approved exports from the 456 MW Upper Tamakoshi plant because a Chinese company carried out its civil construction. Its output cannot be sold across that border.

This shows that power trade is shaped by policy as well as engineering. Who builds a project, who finances it and where its parts come from can all affect where its electricity may be sold. A developer has to plan for those conditions from the start, not after the plant is complete.

For Nepal, the agreement signed with India in January 2024 sets the larger goal. Under it, Nepal plans to export 10,000 MW of electricity over the next ten years. Meeting that goal depends on plants being built and on lines that can carry the power.

The lines that carry power across the border

Cross-border transmission lines decide how much power can actually move. The Dhalkebar-Muzaffarpur 400 kV line has a capacity of 1,000 MW. The Post also gives figures for the Dhalkebar-Sitamarhi link of 1,400 MW for imports and 1,650 MW for exports.

A newer link is planned between Butwal and Gorakhpur. It is expected to start with imports of up to 130 MW and exports of up to 200 MW, and its substation is expected by December 2027. Each new line adds a route, but every line has a limit set by its voltage, conductors and substations.

When generation grows faster than transmission, surplus power has nowhere to go. That makes the grid as important as the dams. Planning both together is how a country turns installed capacity into electricity that reaches users and buyers.

What to study if this interests you

Civil engineering students can follow the construction side: dam and tunnel design, sediment handling in Himalayan rivers, rock support and project scheduling. A progress percentage like Arun-III's comes from measuring completed work against a planned schedule, a skill taught in construction management.

Electrical and electronics students can follow the grid side: how a 400 kV line is rated, why substations limit transfer and how power is balanced across a border. The import and export figures in this report are capacity limits that come from that engineering, not just from policy decisions.

Both groups can practise reading project reports with care. Separate what has been completed from what is planned, and what is financed from what is built. The source reports progress and plans as stated, and it does not give a date for most of the projects. Holding those distinctions is the habit that makes a good planning engineer.

Words in this story

Installed capacity
The maximum power a plant can produce when all its units run at full output, measured in megawatts (MW).
Transmission line
A high-voltage line that carries electricity from a power plant to substations and the wider grid, or across a border.
Substation
A facility that changes voltage levels and connects lines, often the point that limits how much power can be transferred.

Where this comes from

Written in our own words; no sentence is copied from these reports. Researched with AI assistance and added 17 October 2026; no member of faculty has reviewed this story yet. If you spot a mistake, call 01-5091616 and we will correct it and say so.

Next story: KRW 9.6tnLG Energy Solution leans on grid storage as quarterly revenue rises 27.6%

Added by Imperial College of Engineering. Written 9 November 2026 from the linked sources. Faculty review is pending.