Formerly Janakpur Engineering College (JEC)Affiliated to Tribhuvan University
A toppled steel transmission tower on a flood-scoured riverbank in a Himalayan gorge, engineers in hard hats inspecting it

Nepal’s flood-hit power system: what is reconnecting and what is still cut off

Fallen towers, damaged plants and a new flood in Gorkha left hundreds of megawatts stranded. Repairs, trial generation and new rules are now under way.

AI illustration

BCEBEI

Nepal spent the weeks after its floods counting megawatts it could not use. On 30 September, Radio Nepal reported that about 430 MW was disconnected from the national grid after flood damage to hydropower projects on the Bhotekoshi. Two days later a different problem appeared in Myagdi: plants that were still able to generate had no line to send power through.

  • 430 MWdisconnected from the grid, government figure, 30 September (Radio Nepal)
  • 176 MWsix Myagdi and Mustang plants unable to connect, 2 October (OnlineKhabar)
  • 4 towersfallen on the 220 kV Dana–Khurkot line (OnlineKhabar)
  • 14 projectsdamaged by the August flood, about 783 MW (Energy Ministry, via OnlineKhabar)
  • 3 facilitieshydropower facilities damaged by the 11 October Budhi Gandaki flood (NDRRMA)
  • 30 MWKhani Khola, test generation from 4 October (The Kathmandu Post)

Four separate problems, one grid

The first problem was damage at the plants themselves. The Energy Ministry said the August flood damaged 14 hydropower projects with a combined capacity of about 783 MW, OnlineKhabar reported on 30 September. The Nepal Electricity Authority (NEA) separately said about 190 MW had been disconnected by the floods and landslides that followed the late-September rain. The 430 MW in Radio Nepal’s report was the government’s figure for capacity cut off on that day.

Another view of a toppled steel transmission tower on a flood-scoured riverbank in a Himalayan gorge, engineers in hard hats inspecting it
One fallen tower can cut off every plant on the line (AI illustration)

The second problem was the wires. Kaligandaki flooding brought down four towers on the 220 kV Dana–Khurkot transmission line, at Pokharebagar and Dhirchyang in Annapurna Rural Municipality and at Bhirkate in Dovan, Myagdi, OnlineKhabar reported on 2 October. Six hydropower projects in Myagdi and Mustang with a combined 176 MW could not connect to the national system, and supply to Mustang and Annapurna Rural Municipality was cut. The NEA began repairs and started preparing an alternative line.

The third problem was new. On 11 October a flash flood came down the Budhi Gandaki in Gorkha. NDRRMA’s Situation Report #3 of 13 October lists three hydropower facilities among the damage, along with nine bridges and one school. It attributes the flood to a snow avalanche and a major landslide involving glacier ice and debris in the upper Ungdilung Khola. Project-level damage figures had not been published in that report.

The fourth is the rules. The Electricity Regulatory Commission is drafting a disaster-resilient framework for energy infrastructure, and a Post Disaster Needs Assessment under the National Planning Commission is collecting data. A preliminary rapid assessment put energy-sector damage at about Rs 134 billion. Officials have discussed risk-based insurance premiums and concessional loans, but none of that was final when OnlineKhabar reported it.

The engineering behind it: a plant can run and still deliver nothing

A hydropower plant is one link in a chain. Water turns the turbine, the generator makes electricity, a step-up transformer raises the voltage, a transmission line carries it to a substation, and the grid shares it out. A break at any link stops the delivery. The Myagdi case shows the expensive version: the six plants were stranded because towers fell on the shared line, not because their turbines failed.

A hydropower plant sends power along a transmission line to a substation and the grid. Fallen towers break the line, and a dashed alternate line bypasses the break.
In Myagdi, four fallen towers on one 220 kV line stranded six plants with 176 MW (OnlineKhabar, 2 October). A second route keeps some power moving.Diagram: Imperial College of Engineering, drawn from the sources at the foot of this story.

This is why engineers talk about a single point of failure. When several plants feed one corridor, that corridor carries all of their output and all of their risk. A second route, even a lower-capacity one, lets some power keep flowing while the main line is rebuilt. Before an alternate line is switched on, engineers still have to check conductor clearances, protection relay settings and how much load the new path can carry.

Repairing a tower in a river valley is slow for practical reasons. Crews must reach the site, often on damaged roads, inspect the foundation and the ground around it, and restring conductors safely with the line isolated and earthed. A tower that fell because the riverbank under it was washed away cannot simply be put back in the same place.

The numbers in the reports are snapshots. The 430 MW, 190 MW, 176 MW and 783 MW figures come from different dates, different agencies and different definitions: capacity disconnected, capacity unable to connect, capacity damaged. Adding them would count some plants twice. A careful reader keeps each number with its date and its source.

Signs of recovery

Some plants are coming back. The 30 MW Khani Khola Hydropower Project in Dolakha began test generation on 4 October and was feeding the grid, The Kathmandu Post reported on 16 October. Plant manager Ishwar Kandel said commercial operation was targeted for 19 October after a 15-day test period. Floods on 9 July 2024 had damaged its dam site, so the project is a working example of a plant finished after flood damage.

Test generation is the stage where operators prove that the plant and the grid work together: synchronising the generator, checking protection settings, and watching vibration and temperature under load. Those are standard commissioning checks, not a list the newspaper reported for Khani Khola. The 19 October date was a target when the Post reported it.

New investment is also moving. Investment Board Nepal approved Rs 10.75 billion for the 58.9 MW Nar Khola project and Rs 10.42 billion for the 46.72 MW Sani Bheri-3 project, Radio Nepal reported on 9 October. Both are semi-reservoir plants, together 105.62 MW. A semi-reservoir plant keeps a few hours of water behind a low dam so it can generate more in the evening peak. Approval is a milestone, not a sign that construction has started.

An engineer in a hard hat studies a grid diagram on a monitor in a hydropower control room at duskAnother view of a control room engineer checking relay panels against a grid diagram

Bringing a plant back means proving it works with the grid (AI illustration)

What to study if this interests you

Hydropower Engineering (ENCE 403) covers how intakes, headworks and powerhouses are designed, and Engineering Hydrology (ENCE 306) covers the flood flows they must survive. Hydraulics (ENCE 251) is the base for both. For electronics students, Electrical Circuits and Machines (ENEE 154) explains the generators and transformers in the chain, and Engineering Economics (ENCE 307) is where questions like insurance, loans and who pays for stronger design are worked through.

A useful class exercise is to draw the chain for one real plant from this story: river, intake, powerhouse, line, substation. Mark each link, then ask which single failure would stop delivery and how long each would take to repair. That one sketch explains why a fallen tower in Myagdi mattered to six companies at once.

Words in this story

Transmission line
High-voltage wires on towers that carry electricity from power plants to substations far away.
Single point of failure
One part of a system whose failure alone stops the whole system from working.
Test generation
The trial period when a new plant first sends power to the grid so operators can check every system under load.
Semi-reservoir plant
A hydropower plant that stores a few hours of river flow so it can produce more power at the evening peak.

Where this comes from

Written in our own words; no sentence is copied from these reports. Researched with AI assistance and added 17 October 2026; no member of faculty has reviewed this story yet. If you spot a mistake, call 01-5091616 and we will correct it and say so.

Next story: 268 mNepal contractor rebuilds a 268-metre Trishuli footbridge in a month

Added by Imperial College of Engineering. Written 18 October 2026 from the linked sources. Faculty review is pending.