Floods push the Siddhababa tunnel opening back to mid-January
The 1,126 m tunnel near Butwal was due before Dashain. Flood damage on two river corridors delayed the electrical and safety equipment it still needs.
For you: A tunnel can have its rock excavated and still be unable to open, because lighting, ventilation, alarms and emergency telephones have to be installed and tested first. This project shows that the electrical and electronic fit-out is a critical path item, and that a flood on a supply route can move the date as much as the rock can. It is also a live case of how civil and electronics engineers share one project.