Golden Gate Bridge begins final phase of its seismic retrofit
Work on the towers and suspension spans started with night lane closures on 5 October.
Overnight lane closures began on the Golden Gate Bridge in San Francisco on 5 October 2026 as work started on the last phase of its earthquake retrofit, Construction Briefing reported. Contractor Halmar International will strengthen the two main towers and the suspension spans under a first contract worth about 864 million US dollars. The bridge stays open throughout.
- 28energy dissipation devices to be installed
- $41.35 mcontingency budget for the towers and side spans contract
- 40 millionvehicles a year carried by the bridge
- 1989year of the Loma Prieta earthquake that started the retrofit
- $395.7 min federal Bridge Investment Program funds for the work
What happened
The Golden Gate Bridge, Highway and Transportation District, which owns the bridge, calls this work Phase 3B. It is the final part of a retrofit programme that began after the 1989 Loma Prieta earthquake. According to Construction Briefing, the bridge showed no observed damage in that earthquake, but later studies found weaknesses that could matter in a larger one. The district then split the strengthening into phases.
Earlier phases strengthened the Marin approach viaduct, the San Francisco approach viaduct and anchorage housing, and the Fort Point arch and southern pylons. The district says those phases already allow the bridge to withstand a large earthquake safely. The final phase aims for more. It is meant to keep the bridge usable after a large earthquake, so that emergency services can rely on it in the hours and days that follow.
Crews began by lowering temporary access platforms and materials beneath the roadway during overnight closures. At least one lane stays open in each direction. The bridge is about 1.7 miles, or 2.7 km, long and carries up to 40 million vehicles a year, so closing it for the work was not an option.
The district has divided the construction into two contracts. Contract 1 covers the two main towers and the two side spans. Contract 2 will cover the main span. The district's board approved Contract 1 in October 2025 at 863,949,008 US dollars, with a contingency budget of 41.35 million dollars. The total project budget for Contract 1 rose to about 1.01 billion dollars. Construction Equipment Guide reported that this stage is expected to take about six years.
The engineering behind it
A suspension bridge carries its deck on vertical cables called suspenders, which hang from main cables draped over tall towers. The towers carry large vertical loads and must also resist sideways forces. In an earthquake, the ground shakes the foundations, and the towers, deck and cables all move in different ways. Strong shaking can overload connections, buckle braces or cause parts to collide. This is a general description of how such bridges behave.
The board document lists the work in detail. It includes retrofitting the base of the tower legs, strengthening the stiffening trusses under the deck, retrofitting the suspender rope supports, strengthening floor beams and replacing the top lateral bracing. Old thermal expansion joints in the roadway will be replaced with isolation deck joints. Pylon and tower connections will be strengthened, and select deck support pedestals replaced. Structural steel will be cleaned and painted, with old lead paint removed.
One item stands out. The contract includes installing 28 solid state energy dissipation devices. In general, such devices act like shock absorbers. When the structure moves during an earthquake, they absorb part of the energy and turn it into heat, so less energy goes into bending and damaging the main members. Isolation joints serve a related purpose, allowing parts of the bridge to move without forcing each other.
The work also shows performance-based thinking. Rather than only preventing collapse, the design aims for a level of performance after the earthquake, here keeping the bridge open for emergency use. A structure that must keep working after a disaster is often called a lifeline structure. Designing for that goal usually needs more strengthening than designing only to prevent collapse.
What it means in Nepal
The sources do not discuss Nepal, so this section is about the skills behind the project. The main lesson is that much engineering work is on existing structures, not new ones. Retrofitting a bridge while traffic still uses it needs careful staging, temporary works and safety planning. Engineers must understand how an old structure was designed and built, find where it is weak, and design new parts that fit around the old ones.
The project also shows how costs are checked. The district used a contracting method in which the builder joins the project during design. Before the price was agreed, three separate estimates were made by the builder, the designer and an independent cost estimator. The agreed price was within about 3 to 5 percent of the other two. The team also kept a risk register listing possible problems, their chance of happening and their likely cost. These are practical tools that apply to any large public project.
A third lesson is about funding and public responsibility. The district's board document shows that the original budget of 870 million dollars came from federal bridge funds, state funds and the district's own reserves. When the agreed price came in higher, the extra 141.7 million dollars came from district reserves. Engineers on public projects often have to explain such increases to a board in plain language, with the risks and the reasons laid out clearly.
What to study if this interests you
Theory of Structures II, ENCE 252, in the fourth semester of BCE, covers the analysis of indeterminate structures and how forces move through a frame or truss. Design of Steel Structures, ENCE 303, in the fifth semester, teaches the design of steel members, bracing and connections, which make up most of this retrofit. Estimating and Costing, ENCE 351, in the sixth semester, covers how quantities and rates become a project cost, the skill behind the three independent estimates on this contract.
Behind all of this is a sound understanding of how structures respond to loads that change with time. Engineering Mathematics III, ENSH 201, in the third semester, introduces the differential equations and series methods that later support the study of vibration and earthquake response, and it has a full guide on this site. Students who enjoy this area can follow it into structural dynamics and earthquake engineering at a more advanced level.
Words in this story
- Seismic retrofit
- Strengthening an existing structure so it performs better in an earthquake.
- Energy dissipation device
- A part that absorbs the energy of shaking, like a shock absorber, so the main structure is damaged less.
- Lifeline structure
- A bridge, road, pipe or other structure that must keep working after a disaster for rescue and recovery.
- Stiffening truss
- A deep steel frame along a suspension bridge deck that spreads loads and limits bending and twisting.
Where this comes from
- Construction Briefing, 6 Oct 2026
- Golden Gate Bridge, Highway and Transportation District (board agenda item, Contract 2025-B-052), 23 Oct 2025
- Construction Equipment Guide, 2025
The news itself rests on one source; any other link is background or from the same publisher. Written in our own words; no sentence is copied from these reports. Researched with AI assistance on 11 October 2026; no member of faculty has reviewed it yet. If you spot a mistake, call 01-5091616 and we will correct it and say so.








